    ​Rand Water is planning to do maintenance work and various cross connections on their newly constructed H42 pipeline on the dates listed below: 

    1.         25 to 26 February 2020 from 04:00 to 07:00 (27 hours). Complete connection tie-in in Andeon between H29 and the new H42 pipeline at the end connection.  

    2.         3 to 4 March 2020 from 05:00 to 16:00 (35 hours). Complete connection tie-ins (Atteridgeville Prison) between the H30 and the new H42 pipeline.  

    3.         10 to 11 March 2020 from 05:00 to 21:00 (40 hours). Complete connection tie-ins (Atteridgeville Prison) between H28 and the new H42 pipeline.  

    4.         17 to 18 March 2020 from 04:00 to 04:00 (24 hours). Complete connection tie-in at Andeon between H18 and the new H42 pipeline.  

    Rand Water will continue to supply water through alternative pipelines during these days to all Tshwane reservoirs and meters connected to this line. This scheduled work will thus not result in any water interruptions, but there will be a drop in water pressure. 

    The City of Tshwane sincerely apologises for any inconvenience that may be encountered because of the scheduled work. 

    We appeal to all residents to utilise water sparingly during this time.